Hove ‘Passivhaus’ Tour

Hove ‘Passivhaus’ Tour

This year’s International Passive House Open Days event provides an exciting opportunity to view Hove ‘Passivhaus’ which has now been occupied for almost a year. While the house was not formally certified it meets the Passivhaus criteria and has been registered with the Passive House Database. Hove ‘Passivhaus’ will be open for two tours at 10am and 11.30 on Saturday 10th November and places must be reserved through jim@jimmillerdesign.co.uk.

 

Hove ‘Passivhaus’ is working

The boiler went off by accident in January (so the building was unheated) but being so well insulated nobody noticed for 3 days!  That’s what you get from a Passivhaus – surely how all new building should function in the 21st century?

Hove ‘Passivhaus’ nearly there

Hove ‘Passivhaus’ nearly there

The internal fit out is nearing completion, moving on to the driveway next month.  The external solar roller blinds still allow a fair amount of visible light through as can be seen in the third image (where the top window is protected but the lower window is not).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Hove ‘Passivhaus’ nears completion

Hove ‘Passivhaus’ nears completion

Been a while but the project nears completion with a classic pre-christmas move in date, ‘ready or not’!  Intermediate air test result of 0.6 ACH means the house is likely to be a non-certified Passivhaus.

 

 

 

Hove ‘Passivhaus’ TOUR

So the ‘Passivhaus’ new build tour at 31 Old Shoreham Road, Hove BN3 6NR is tomorrow evening, Tuesday 20th June at 7pm.  Please arrive on time as I expect we will have to lock the gate when the tour begins.  The site is just off the junction of Shirley Drive and Old Shoreham Road and there is parking nearby but not on site.  Hard hats are mandatory so please bring one if you have one as there are only one or two spares on site.  I imagine the tour will take around an hour and a half and we may retire to a local pub afterwards.  The tour is fully booked.

Hove ‘Passivhaus’ TOUR

There will be a site tour of the ‘Passivhaus’ new build at 31 Old Shoreham Road, Hove BN3 6NR at 7pm on Tuesday 20th June.  The timber frame will be partially complete so it’s an exciting time to see the build.  Hard hats are mandatory so please bring one if you have one as there are only one or two spares on site.  I imagine we will retire to a local pub afterwards.  Please let me know if you plan to attend, even as late as on the day / evening.

Hove ‘Passivhaus’ timber frame

Hove ‘Passivhaus’ timber frame

The timber frame has arrived from Latvia with panels fully assembled including insulation, plasterboard and even conduit ready to receive wiring!  The photos below show just one day on site.  It will be interesting to see how the plastic sheeting handles the British weather.

days work

crane

conduitinsulationservices

Hove ‘Passivhaus’ concrete

Hove ‘Passivhaus’ concrete

So the concrete works are complete with the polished concrete lower ground floor, gym ‘box’ and rear retaining wall ready for the timber frame in April and the gabions are coming along well

FrontWholeTo road gabions

 

 

Hove ‘Passivhaus’ Isoquick

Hove ‘Passivhaus’ Isoquick

The Isoquick is due to be installed, starting this Wednesday and taking 3 – 4 days.  If anyone is interested in a site visit then drop me a line and I’ll make arrangements.  Here is an example from another job:

isoquick-example

Hove ‘Passivhaus’ foundations

Hove ‘Passivhaus’ foundations

The original concept was to support the entire building on an insulated raft system, Isoquick, which is an elegant solution avoiding footings and the associated detailing and cold bridging issues but as it turned out the building (at 4 stories) was too heavy and we’ve ended up with a hybrid foundation with Isoquick at the rear but strip footings to the front.  Here you can see the site being prepared to install the 300mm deep Isoquick on to the drainage layer flush with the top of the strip footings.

drainage-layer

Hove ‘Passivhaus’ gabion filling

Hove ‘Passivhaus’ gabion filling

The rocks are placed into the gabion by hand and the face stone is laid carefully against the outer mesh.  Also note the wire bracing across the centres of the baskets to help reduce deformation.

gabion-filling

Hove ‘Passivhaus’ gabion fill

Hove ‘Passivhaus’ gabion fill

The first section of structural gabion has worked out well and the contractors have managed to adjust the tilt of the gabions from 6 degrees (at the back of the photo) to 3 degrees (at the front) without the use of bespoke baskets

gabion-fill

gabion-fill-detail

Hove ‘Passivhaus’ gabion baskets

Hove ‘Passivhaus’ gabion baskets

So the structural gabions you see below are inclined at 6 degrees on their concrete base but the gabion cladding to the garage (in the background) will be vertical so we have to feather the two which is going to be a bit of an experiment!  There’s also an image showing the wire holding the baskets together with the faster but more visually intrusive helicoil option in the background.

gabion-baskets wire-detail

 

Hove ‘Passivhaus’ gabion materials

Hove ‘Passivhaus’ gabion materials

The drive is cut into the sloping site and both sides will use gabions (rock filled metal wire baskets) instead of concrete to retain the ground, primarily for aesthetic reasons but also to reduce cement usage and for easy maintenance.  The fill will be grey limestone but there will be areas of snapped flint which will be sourced from just down the road from fields behind Telscombe cliffs.

gabion-materials

Hove ‘Passivhaus’ demolished

Hove ‘Passivhaus’ demolished

So the old house is gone, reduced to a pile of rubble.  Most of interior found a new home.  As it’s too expensive to recycle the rubble on site, it will be trucked away to be turned into hardcore and then perhaps even brought back to site in a few weeks / months to be used in the foundations, but at least it’s all local!

house-demolished

Hove ‘Passivhaus’ demolition

Hove ‘Passivhaus’ demolition

With the garage shell complete it’s time for the 1930’s house to be demolished after it’s 80 year life.  I always wonder how much / well the rubble is recycled by the waste companies

house-demolition

Hove ‘Passivhaus’ garage shell

Hove ‘Passivhaus’ garage shell

The garage concrete shell is now complete.  Set into the ground on two sides, it will have a hedge to the south and decking over and I wonder how the internal temperature will vary.  It’s thermally massive at 300mm concrete all round but insulation was dropped at the last minute due to cost.  I expect the thermal mass will seriously dampen the daily fluctuations but the temperature will vary considerably over the year and won’t be much good for storing wine!  We did look at a simple ground loop to chill a small compartment in the garage as a wine store but it seemed overly complicated in the end.

garage-complete

Hove ‘Passivhaus’ garage slab

Hove ‘Passivhaus’ garage slab

Just managed to get the slab down and ‘commence works’ before the planning permission expires next week!   Interestingly the concrete supplier uses 50% GGBS as standard.  Note the kicker was formed as part of the slab to avoid an additional water bar.

Garage slab

Hove ‘Passivhaus’

Hove ‘Passivhaus’

This blog will follow the construction of a 6 bedroom house in Hove designed and built to Passivhaus standards.  As the completed project may not end up being certified, the house may not in the end be a true Passivhaus.  The structure will be a turnkey timber frame built in Latvia and shipped over in panels with plasterboard and service runs already installed.  The contractor has just started on site and I’ll keep you posted as things progress!

sketchup-31osr

Save